NSW LEGISLATION.

This Act is the Building and Construction Industry Security of Payment Act 1999.

(1) The object of this Act is to ensure that any person who undertakes to carry out construction work (or who undertakes to supply related goods and services) under a construction contract is entitled to receive, and is able to recover, progress payments in relation to the carrying out of that work and the supplying of those goods and services.
(2) The means by which this Act ensures that a person is entitled to receive a progress payment is by granting a statutory entitlement to such a payment regardless of whether the relevant construction contract makes provision for progress payments.
(3) The means by which this Act ensures that a person is able to recover a progress payment is by establishing a procedure that involves—

(a) the making of a payment claim by the person claiming payment, and
(b) the provision of a payment schedule by the person by whom the payment is payable, and
(c) the referral of any disputed claim to an adjudicator for determination, and
(d) the payment of the progress payment so determined.

(4) It is intended that this Act does not limit—

(a) any other entitlement that a claimant may have under a construction contract, or
(b) any other remedy that a claimant may have for recovering any such other entitlement.

Scope

Contents:

Long Title
Part 1: Preliminary
Part 2: Rights To Progress Payments
Part 3: Procedure For Recovering Progress Payments
Division 1: Payment Claims And Payment Schedules
Division 2: Adjudication Of Disputes
Division 2A: Claimant's Rights Against Principal Contractor
Division 3: Claimant's Rights To Suspend Construction Work
Division 4: General
Part 3A: Investigation And Enforcement Powers
Division 1: Preliminary
Division 2: Information Gathering Powers
Division 3: Entry To Premises
Division 4: Offences
Part 4: Miscellaneous
Schedule 1: (Repealed)
Schedule 2: Savings And Transitional Provisions
Historical Notes